100 Gordon Street

100 Gordon Street was a City-owned property, in downtown Nanaimo, directly across the street from the Vancouver Island Conference Centre.  Great Canadian Casino and Port Place Shopping Centre are to the south across Cameron Road.  The Port Theatre, Library and Diana Krall Plaza are to the north across Museum Way.

The City of Nanaimo issued a Request for Offers for 100 Gordon Street. Proponents were asked to provide background information on their proposed project, timing and the price they were willing to pay for the property. Offers were required to be submitted by January 27, 2017. Six proposals were received by the deadline.

At the June 19, 2017 Council meeting, ‘Approval in Principle’ was granted by Council for the disposition of the property to PEG Development.

The property was sold to PEG Development on December 7, 2017 for $750,000. 

The City has the right to repurchase the property for $750,000 should PEG Development not meet its obligations and be under construction within two years.

The Development Permit proposes a 9-storey, 172 room hotel.

100GordonStreet

 

Gallery

  • Progress

    April/May 2021 Update:

    Through April and May the erection of the 5th to 7th floors of steel will be completed. Steel q-deck and concrete topping have been completed on the lower floors, q-deck and concrete will follow behind the steel erection. Mechanical rough-in and steel stud framing have started on the 2nd floor and will follow the concrete toping up the building. It's anticipated cladding panel installation will start in June.

    Picture1


  • Documents
  • Details

     

  • Background

    January/February 2021 Update:

    Work for the Nanaimo Courtyard Marriott project is well underway with ground works pushing forward through the winter months. A few highlights are listed below:

    • Concrete cores continue to climb and vary between the 3rd and 6th floor in elevation. These core walls continue to the 9th floor of the building.
    • Under slab plumbing and electrical work continue.
    • Site back-fill continues, all native material has been returned to site to be used to back-fill foundation.
    • Temporary power has been connected to site which has been pulled from the permanent power connection point.
    • Tower crane is scheduled to be placed late February.
    • Steel erection will begin at the start of March.

    December 2020 Update:

    • Ground stabilization including rapid impact compaction, rock anchors and mini piles has been completed
    • Rock stabilization on east property line is complete
    • Completion of concrete footings, grade beams and walls is in progress, most pad and strip footings have been placed
    • Structural concrete core walls for elevators, stairs and structural T-wall is in progress, these core walls continue to the 9th floor of the building
    • Site back-fill has begun where footings are complete
    • Underground mechanical and electrical work is in progress

     

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.

Privacy Policy