Jingle Pot @ Westwood - New Signal - VEH

Back to map

Project Description

The Jingle Pot & Westwood Road Intersection & Utility Upgrade Project includes: -Upgrade from a Two-way Stop Control to Traffic Signal -Sanitary Sewer & Watermain Utility Upgrades -Additional Sidewalks & Bike Lanes

General Considerations

  • Typical hours of work for this project will be Monday to Friday, 7:00 AM to 9:00 PM, with work after hours and weekends as required.
  • Construction noise and vibration should be expected during working hours.
  • Residents and businesses will be notified 24 hours in advance of any scheduled water shutdowns.
  • Anticipate traffic pattern changes, road closures, and detours at times.
  • If you live in the area and have young children, please advise them of the dangers of construction and the limited visibility of heavy equipment and trucks.
  • Landscape restoration will be done at the end of the project.

Cost Estimate:

Estimate Construction Start Date: May 2019

Estimate Construction Completion Date: August 2019