BP125454 - 1608 Bowen Road

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP125454 - 1608 Bowen Road
Neighbourhood: Northfield    
Street Address: 1608 Bowen Road
Type of Application: Commercial / Multi / Industrial
File Number: BP125454
Date Application Submitted: April 23, 2019
Application Description: Four storey residential building - 48 Residential units, Group C, 3.2.2.51, 4 storey, sprinklered with standpipes in exit stairwells, fire alarm and 775.9 m2 open Parkade. Building area 1110.66 m2. Total gross floor area 3677.2 m2 (including stairwells and elevators) 1st storey = 339 m2 ; 2nd storey 1110.66 m2; 3rd storey 1114.74 m2; 4th storey 1112.8 m2. 1 Hour FRR/FS 50 STM between residential suites, 1 Hour FRR/FS for public corridor, floor assemblies and loadbearing supports, storage rooms, exit stairs, elevators and machine room; all doors in fire separations to be self-closing with positive latching mechanisms. Rated roof provided for termination vertical 1 hour FRR/FS. Vertical service spaces 45 min FS/FRR.

REVISION: June 11/20 - Change to bathroom layout in units 203, 303 & 403. This affected plumbing and sprinklers.
Application Status: COMPLETED
Permit Value: $6,116,714.00
Builder: SAYWELL CONTRACTING LTD
Issued Date: October 08, 2019
File Close Date: November 27, 2020
Expiry Date: October 07, 2021

Process Steps

Task Status
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
FIRELINE

Fireline for the sprinkler system must be complete and visable for inspection.

PARTIAL
FIRELINE

Fireline for the sprinkler system must be complete and visable for inspection.

PASSED
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PASSED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PASSED
STORM CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
STORM CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
STORM CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
STORM CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
STORM CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
STORM CONNECTION

Pipe and connection must be visible for inspection.

PASSED
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

CANCELLED
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PASSED
WATER CONNECTION

Pipe and connection must be visible for inspection.

CANCELLED
WATER CONNECTION

Pipe and connection must be visible for inspection.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

CANCELLED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

FAILED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

FAILED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

FAILED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL

All fixtures must be in place.

FAILED
PLUMBING FINAL

All fixtures must be in place.

PASSED
APPROVAL-ENGINEERING

Approval required prior to Occupancy

APPROVED
APPROVAL-FIRE-OLD

Approval required prior to Occupancy

COMPLETED
APPROVAL-PLANNING

Approval required prior to Occupancy

APPROVED
OCCUPANCY FAILED
OCCUPANCY FAILED
OCCUPANCY PASSED

2020-11-27

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy