BP117605 - 691 Bowen Road - SFD with Suite -- Scanned

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP117605 - 691 Bowen Road - SFD with Suite -- Scanned
Neighbourhood: University District    
Street Address: 691 Bowen Road - SFD with Suite -- Scanned
Type of Application: Single / Two Family Dwelling
File Number: BP117605
Date Application Submitted: July 26, 2012
Application Description: Construction of 2 storey Single Family Dwelling w/ secondary suite and unfinished portion of basement on a slab-on-grade.

August 22, 2012 - Builder has re-excavated to solid bearing. Excavation inspection being called to confirm
October15, 2012, Increase size of Secondary Suite and revise layout of Suite....MLB

Revision: 2012-20-12, Adding garage door, removing posts and beams, going with a 6 ft cantilevered deck. Removing window below grade. Adding 4" curb wall to foundation.

Revision: Jan 02, 2012. Adding one 4x4 and 4x2, deleting two other windows, moving garage man door to other side of stairwell and making closet smaller. JDB
Application Status: COMPLETED
Permit Value: $247,515.25
Building Area: 278.61 M2
2,998.93 ft2
Issued Date: August 16, 2012
File Close Date: May 02, 2013

Associated Properties

Address Zone More
691 BOWEN ROAD R1 Property Report

Process Steps

Task Status
EXCAVATION

Excavation of soil, prior to placing forms.

FAILED
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

PASSED
PERIMETER DRAIN

For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering

PASSED
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible

PASSED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

PASSED
STORM CONNECTION

Pipe and Connection must be visible for inspection

PASSED
SANITARY CONNECTION

Pipe and Connection must be visible for inspection

PASSED
WATER CONNECTION

Pipe and Connection must be visable for inspection

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval

PARTIAL
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection

PASSED
OCCUPANCY-OLD

Exterior of house must be complete including stairs, decks, handrails, porches and exterior finish

PASSED

2013-05-01

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy