BP117041 - 1815 Bowen Road -- Scanned

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP117041 - 1815 Bowen Road -- Scanned
Neighbourhood: Northfield    
Street Address: 1815 Bowen Road -- Scanned
Type of Application: Commercial / Multi / Industrial
File Number: BP117041
Date Application Submitted: March 08, 2012
Application Description: To construct a one storey fitness centre building on this site (VI Fitness Centres for women)

Group A2 Occupancy Part 3 building 3.2.2.27 combustible or non-combustible construction - roof unrated one storey 895 square meters building area sprinklered with fire alarm system. No washroom facilities have been provided for males in this womens only facility. Any inclusion of males in this facility will require alterations to the building to provide the appropriate washroom facilities.
Application Status: COMPLETED
Permit Value: $800,000.00
Builder: WINDLEY CONTRACTING (2010) LTD
Issued Date: May 24, 2012
File Close Date: December 10, 2012

Associated Properties

Address Zone More
1815 BOWEN ROAD COR3 Property Report

Process Steps

Task Status
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PASSED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PARTIAL
PLUMBING FINAL-OLD

All fixtures must be in place.

PARTIAL
OCCUPANCY-OLD FAILED
OCCUPANCY-OLD FAILED
OCCUPANCY-OLD FAILED
OCCUPANCY-OLD FAILED
OCCUPANCY-OLD PASSED

2012-12-10

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.