BP121567 - 105-1825 Bowen Road

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP121567 - 105-1825 Bowen Road
Neighbourhood: Northfield    
Street Address: 105-1825 Bowen Road
Type of Application: Leasehold Improvements
File Number: BP121567
Date Application Submitted: January 07, 2016
Application Description: Neon Nail & Hair Salon - Complete and Occupy - 138 m2 - Group D, Sprinklered with fire alarm. Installing 8 foot sinks, 2 hand sinks, 2 treatments rooms each with hand sinks. 1 staff room with sink and 1 universal washroom. Emergency lighting. Existing exits. Complete 45 min. FRR/FS suite separation. Occupant load = 10 persons.

REVISION JUNE 28, 16 - Moved wall and changed door from sliding to swing

Building area 960 m2 designed to BCBC 2012 3.2.2.61 Group D up to 2 storeys and 3.2.2.67 Group E up to 2 storeys. Combustible construction 45 minute rated fire separation at floor, supports, second storey stairwell, second storey exit and elevator / mechanical rooms.
Application Status: COMPLETED
Permit Value: $70,000.00
Building Area: 136.90 M2
1,473.58 ft2
Builder: POSH CONSTRUCTION LTD
Issued Date: January 26, 2016
File Close Date: June 30, 2016
Expiry Date: January 25, 2018

Associated Properties

Address Zone More
105   1825 BOWEN ROAD COR3 Property Report
1825 BOWEN ROAD COR3 Property Report

Process Steps

Task Status
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visible for inspection.

PARTIAL
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval.

FAILED
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval.

PARTIAL
PLUMBING FINAL-OLD

All fixtures must be in place.

PARTIAL
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PARTIAL
FINAL-OLD

Final Approval as per requirements on plans.

FAILED
FINAL-OLD

Final Approval as per requirements on plans.

PASSED

2016-06-30

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy