BP119044 - 131/133/135/137/139 - 1720 Dufferin - PH 5 - MULTI- FAMILY DEVELOPMENT

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP119044 - 131/133/135/137/139 - 1720 Dufferin - PH 5 - MULTI- FAMILY DEVELOPMENT
Neighbourhood: Northfield    
Street Address: 131/133/135/137/139 - 1720 Dufferin - PH 5 - MULTI- FAMILY DEVELOPMENT
Type of Application: Commercial / Multi / Industrial
File Number: BP119044
Date Application Submitted: September 11, 2014
Application Description: PH 5 - MULTI- FAMILY DEVELOPMENT DESCRIPTION
65 units in 22 buildings - 15 duplex and 7 - 5 unit townhouses
This permit is for 1 - 5 unit townhouse - Building 2 -(Type A) 2 storey on slab, with 1 hour fire separation between each unit, sprinklered

131/ 133,/135,/137,/139 - 1720 Dufferin - 472.13m2 GFA, 5 unit townhouse, sprinklered
revised April 10, 2015 added washroom to each unit. JB
Application Status: COMPLETED
Permit Value: $478,160.44
Builder: GABLECRAFT WESTHILL LP
Issued Date: April 07, 2015
File Close Date: October 30, 2015
Expiry Date: April 07, 2017

Associated Properties

Address Zone More
131   1720 DUFFERIN CRESCENT R8 Property Report
139   1720 DUFFERIN CRESCENT R8 Property Report
137   1720 DUFFERIN CRESCENT R8 Property Report
135   1720 DUFFERIN CRESCENT R8 Property Report
133   1720 DUFFERIN CRESCENT R8 Property Report

Process Steps

Task Status
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

CANCELLED
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PASSED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PASSED
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PASSED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PASSED
STORM CONNECTION

Pipe and connection must be visible for inspection.

PASSED
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PASSED
WATER CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
WATER CONNECTION

Pipe and connection must be visible for inspection.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
INTERIOR BRACED WALL PANELS

The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound.

PARTIAL
INTERIOR BRACED WALL PANELS

The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound.

PASSED
SPRINKLER FINAL-OLD

Sprinkler system must be complete and operating as intended.

PASSED
OCCUPANCY-OLD FAILED
OCCUPANCY-OLD PASSED

2015-10-30

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy