BP118917 - 104 - 6543 Portsmouth

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP118917 - 104 - 6543 Portsmouth
Neighbourhood: Dover    
Street Address: 104 - 6543 Portsmouth
Type of Application: Leasehold Improvements
File Number: BP118917
Date Application Submitted: August 30, 2013
Application Description: Dr. Michael Stochmal - office

79m2 D occupancy accessible, relocate one w/c add one w/c c/w shower, laundry room and 5 sink rough ins.

2 storey, Part 9 Building. Sprinklered.
Building Area 501.35m2
Lower floor Area 501.35m2 - 'Group D' Occupancy:
Upper floor 372m2 -'Group D' occupancy
45min FS/FRR required for floors, 1hr provided.
45min FRR columns or non combustible required, non combustible provided.(colums are appropriate for support of 45min rated floor BCBC 3.2.2.56)
45min supporting walls required, 1hr provided.
45min FS/FRR required for service shafts 1hr provided.
45min FS/FRR required for roof supporting an occupancy, 1hr provided.
EBF of exit stair on east elevation non combustible cladding non combustible construction 1hr FRR
Application Status: COMPLETED
Permit Value: $90,000.00
Builder: WESTMARK CONSTRUCTION LTD
Issued Date: October 04, 2013
Completed Date: February 26, 2014
Expiry Date: October 05, 2015

Associated Properties

Address Zone More
104   6543 PORTSMOUTH ROAD CD6 Property Report
102   6543 PORTSMOUTH ROAD CD6 Property Report

Process Steps

Task Status
UNDERSLAB PLUMBING

Complete underslab plumbing must be visable.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval.

FAILED
FRAMING

Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
PLUMBING FINAL

All fixtures must be in place.

CANCELLED
OCCUPANCY PASSED
FINAL

Final Approval as per requirements on plans.

FAILED
FINAL

Final Approval as per requirements on plans.

CANCELLED
FINAL

Final Approval as per requirements on plans.

FAILED
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.