BP124121 - 450 Diamond Boulevard
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP124121 - 450 Diamond Boulevard | |
---|---|
Neighbourhood: | Rutherford |
Street Address: | 450 Diamond Boulevard |
Type of Application: | Single / Two Family Alteration |
File Number: | BP124121 |
Date Application Submitted: | February 09, 2018 |
Application Description: |
Legal suite REVISION: add geotech 23.03.2018 REVISION 2018-MAY-03 Move BWP at tub. May 4/18: Revision - new truss layout received, add Structural Engineer for basement pony wall. REVISION 2018-MAY-18 Move rear deck, add front deck, delete front entry roof. REVISION 2018-JUN-28 Update drawings to reflect prior changes. |
Application Status: | COMPLETED |
Permit Value: | $147,000.00 |
Building Area: |
65.96 M2 709.99 ft2 |
Builder: | BOEHM CONSTRUCTION LTD |
Issued Date: | March 12, 2018 |
File Close Date: | July 27, 2018 |
Expiry Date: | March 12, 2020 |
Associated Properties
Address | Zone | More |
---|---|---|
450 DIAMOND BOULEVARD | R5 | Property Report |
Process Steps
Task | Status |
---|---|
EXCAVATION
Excavation of soil, prior to placing forms. |
FAILED |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
FAILED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. |
CANCELLED |
FRAMING
Rough in plumbing & electrical must be complete. |
FAILED |
FRAMING
Rough in plumbing & electrical must be complete. |
FAILED |
FRAMING
Rough in plumbing & electrical must be complete. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. |
FAILED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
FAILED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PASSED |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
FAILED |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
CANCELLED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
CANCELLED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2018-07-27 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.