BP119467 - 223 Commercial Street
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP119467 - 223 Commercial Street | |
|---|---|
| Neighbourhood: | Downtown/Old City | 
| Street Address: | 223 Commercial Street | 
| Type of Application: | Commercial / Multi-Res Alteration | 
| File Number: | BP119467 | 
| Date Application Submitted: | February 25, 2014 | 
| Application Description: | 
                Phase 3:    Complete and occupy (C/O)  Group A2 (Restaurant, Kitchen and Staff room on the first storey) and the offices on the second and third storey.  Includes for C/O for  the office  space on  the first storey.   This permit includes professional engineering for sprinklers ,  plumbing and mechanical (kitchen exhaust systems)  x reference BP118189 for fire separation/fire resistance ratings and base building .  Added on May 15, 2014 c/o for Office on the Main Floor and new universal washroom  Heritage Building, 3 Storeys, Sprinklered, Fire Alarm, First storey, Group A2/ D = 420.38 m2; Second Storey, Group D = 399.39 m2; Third floor, Group D = 376.81 m2. Roof top stairs enclosure = 16.16 m2. Roof-top open deck area = 72.55 m2 Total Building Area =1212 m2. Alternative solutions for unprotected openings, exposed wall face, glazed exit on second and third floor and construction type for A2 under BP118189.  | 
        
| Application Status: | COMPLETED | 
| Permit Value: | $492,000.00 | 
| Building Area: | 
                        1,197.00 M2 12,884.39 ft2  | 
                
| Builder: | RW (BOB) WALL LTD | 
| Issued Date: | March 28, 2014 | 
| File Close Date: | July 23, 2014 | 
| Expiry Date: | March 28, 2016 | 
Associated Properties
| Address | Zone | More | 
|---|---|---|
| 223 COMMERCIAL STREET | DT1 | Property Report | 
Process Steps
| Task | Status | 
|---|---|
| 
                                UNDERSLAB PLUMBING
                                     complete underslab plumbing must be visible.  | 
                            PARTIAL | 
| 
                                ROUGH IN PLUMBING
                                     Rough in plumbing must be complete including potable water piping.  | 
                            PARTIAL | 
| 
                                ROUGH IN PLUMBING
                                     Rough in plumbing must be complete including potable water piping.  | 
                            CANCELLED | 
| 
                                ROUGH IN PLUMBING
                                     Rough in plumbing must be complete including potable water piping.  | 
                            PARTIAL | 
| 
                                ROUGH IN PLUMBING
                                     Rough in plumbing must be complete including potable water piping.  | 
                            PARTIAL | 
| 
                                ROUGH IN PLUMBING
                                     Rough in plumbing must be complete including potable water piping.  | 
                            PARTIAL | 
| 
                                ROUGH IN SPRINKLER
                                     Rough in sprinkler must be complete and visable for inspection.  | 
                            PARTIAL | 
| 
                                FRAMING
                                     Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.  | 
                            PARTIAL | 
| 
                                INSULATION
                                     Insulation and vapour barrier to be complete prior to inspection.  | 
                            PARTIAL | 
| 
                                INSULATION
                                     Insulation and vapour barrier to be complete prior to inspection.  | 
                            PASSED | 
| 
                                PLUMBING FINAL-OLD
                                     All fixtures must be in place.  | 
                            PARTIAL | 
| 
                                FINAL-OLD
                                     Final approval as per requirements on plans.  | 
                            FAILED | 
| 
                                FINAL-OLD
                                     Final approval as per requirements on plans.  | 
                            FAILED | 
| 
                                FINAL-OLD
                                     Final approval as per requirements on plans.  | 
                            
                                PASSED
                                     2014-07-23  | 
                        
| Map | 
|---|
                          View in Google Earth (KML)
                     | 
                
            
            Disclaimer:
            
            The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
            Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
            The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
            
            The Information Provided within this website is for Informational Purposes Only.
            It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.
            
        

 View in Google Earth (KML)