BP119049 - Building 7 - 161, 163, 165, 167, 169 - 1720 Dufferin Crescent
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP119049 - Building 7 - 161, 163, 165, 167, 169 - 1720 Dufferin Crescent | |
|---|---|
| Neighbourhood: | Northfield | 
| Street Address: | Building 7 - 161, 163, 165, 167, 169 - 1720 Dufferin Crescent | 
| Type of Application: | Commercial / Multi / Industrial | 
| File Number: | BP119049 | 
| Date Application Submitted: | December 18, 2014 | 
| Application Description: | 
                PH 11 - MULTI- FAMILY DEVELOPMENT DESCRIPTION  65 units in 22 buildings - 15 duplex and 7 - 5 unit townhouses This permit is for 1 - 5 unit townhouse - Building 7 (Type C1)- 2 storey on slab, with 1 hour fire separation between each unit, sprinklered BUILDING 7 under this permit. 161, 163, 165, 167, 169 - 1720 Dufferin - 621.8m2 GFA, 116.59m2 GFA of garages - 5 unit townhouse.  | 
        
| Application Status: | COMPLETED | 
| Permit Value: | $642,176.01 | 
| Builder: | GABLECRAFT WESTHILL LP | 
| Issued Date: | December 17, 2015 | 
| File Close Date: | August 18, 2016 | 
| Expiry Date: | December 17, 2017 | 
Associated Properties
| Address | Zone | More | 
|---|---|---|
| 161 1720 DUFFERIN CRESCENT | R8 | Property Report | 
| 169 1720 DUFFERIN CRESCENT | R8 | Property Report | 
| 165 1720 DUFFERIN CRESCENT | R8 | Property Report | 
| 167 1720 DUFFERIN CRESCENT | R8 | Property Report | 
| 163 1720 DUFFERIN CRESCENT | R8 | Property Report | 
Process Steps
| Task | Status | 
|---|---|
| 
                                FOOTING/FORMS
                                     Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.  | 
                            PASSED | 
| 
                                PERIMETER DRAIN
                                     For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.  | 
                            PASSED | 
| 
                                UNDERSLAB PLUMBING
                                     complete underslab plumbing must be visible.  | 
                            PASSED | 
| 
                                UNDERSLAB INSULATION
                                     Inspection required prior to placing slab concrete.  | 
                            PASSED | 
| 
                                STORM CONNECTION
                                     Pipe and connection must be visible for inspection.  | 
                            PASSED | 
| 
                                SANITARY CONNECTION
                                     Pipe and connection must be visible for inspection.  | 
                            PASSED | 
| 
                                ROUGH IN PLUMBING
                                     Rough in plumbing must be complete including potable water piping.  | 
                            PASSED | 
| 
                                PAPER/FLASHING/WATERPROOFING
                                     When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.  | 
                            PARTIAL | 
| 
                                PAPER/FLASHING/WATERPROOFING
                                     When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.  | 
                            PASSED | 
| 
                                ROUGH IN SPRINKLER
                                     Rough in sprinkler must be complete and visable for inspection.  | 
                            PARTIAL | 
| 
                                ROUGH IN SPRINKLER
                                     Rough in sprinkler must be complete and visable for inspection.  | 
                            PASSED | 
| 
                                FRAMING
                                     Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.  | 
                            PARTIAL | 
| 
                                FRAMING
                                     Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.  | 
                            PASSED | 
| 
                                INSULATION
                                     Insulation and vapour barrier to be complete prior to inspection.  | 
                            PARTIAL | 
| 
                                INSULATION
                                     Insulation and vapour barrier to be complete prior to inspection.  | 
                            PARTIAL | 
| 
                                INSULATION
                                     Insulation and vapour barrier to be complete prior to inspection.  | 
                            PASSED | 
| 
                                SPRINKLER FINAL-OLD
                                     Sprinkler system must be complete and operating as intended.  | 
                            PARTIAL | 
| 
                                SPRINKLER FINAL-OLD
                                     Sprinkler system must be complete and operating as intended.  | 
                            PASSED | 
| OCCUPANCY-OLD | 
                                PASSED
                                     2016-08-18  | 
                        
| Map | 
|---|
                          View in Google Earth (KML)
                     | 
                
            
            Disclaimer:
            
            The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
            Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
            The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
            
            The Information Provided within this website is for Informational Purposes Only.
            It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.
            
        

 View in Google Earth (KML)