BP131636 - 2351 Jingle Pot Road

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP131636 - 2351 Jingle Pot Road
Neighbourhood: Westwood    
Street Address: 2351 Jingle Pot Road
Type of Application: Single / Two Family Alteration
File Number: BP131636
Date Application Submitted: March 09, 2026
Application Description: New addition to single family dwelling.

2026-JUL-27 REVISION: Remove secondary suite design designation,Remove fire separation, Remove internal doors separating the space from the main house, Kitchen changed to summer kitchen, Laundry sink rough in in bathroom, bathroom layout change, French doors removed and replaced with single entry door on adjacent wall, Bar sink counter shortened, Crawl space access moved and framing modification in flooring system, seismic design change to accommodate floor plan design change.
Application Status: ACTIVE
Permit Value: $19,000.00
Building Area: 48.69 M2
524.09 ft2
Issued Date: April 22, 2026
Expiry Date: April 22, 2028

Associated Properties

Address Zone More
2351 JINGLE POT ROAD AR2 Property Report

Process Steps

Task Status
EXCAVATION

Excavation of soil, prior to placing forms.

PASSED
FOOTING/FORMS

Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PASSED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PASSED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PASSED
UNDERSLAB RADON

Inspection of granular layer and piping

PASSED
ROUGH IN PLUMBING

Rough In plumbing must be complete including water piping.

PARTIAL
ROUGH IN PLUMBING

Rough In plumbing must be complete including water piping.

CANCELLED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

CANCELLED
ROUGH IN PLUMBING

Rough In plumbing must be complete including water piping.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

PARTIAL
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

PASSED
FRAMING

Rough in plumbing & electrical must be complete.

CANCELLED
INTERIOR BRACED WALL PANELS

The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound.

CANCELLED
INTERIOR BRACED WALL PANELS

The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound.

PASSED
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.