BP131618 - #103 - 5190 Dublin Way, (TEYA, Bubble Tea)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP131618 - #103 - 5190 Dublin Way, (TEYA, Bubble Tea) | |
|---|---|
| Neighbourhood: | Pleasant Valley |
| Street Address: | #103 - 5190 Dublin Way, (TEYA, Bubble Tea) |
| Type of Application: | Leasehold Improvements |
| File Number: | BP131618 |
| Date Application Submitted: | March 02, 2026 |
| Application Description: |
Tenant Improvement for Low occupant load A-2 in Group D occupancy, 94.2 m2. Work includes removing partition walls, changes to plumbing and sprinkler systems. Part 9 - Group D, 2 storeys, sprinklered/fire alarm, construction provided 1 hr FRR/FS for future considerations of occupancies.. Provided 1 hr FRR for exterior walls for North , South and West Wall. 45 min required. Single exit permitted, emergency lighting required to illuminate path of travel to exit. 1 hour FRR/FS for the suite separations and floor assemblies. 2026-JUL-29 REVISION: Sink and ice bin have been switched to reflect the actual installed layout. |
| Application Status: | ACTIVE |
| Permit Value: | $100,000.00 |
| Issued Date: | May 04, 2026 |
| Expiry Date: | May 04, 2028 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 103 5190 DUBLIN WAY | CD5 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PARTIAL |
|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PASSED |
|
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
FAILED |
|
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visible for inspection. |
PARTIAL |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PARTIAL |
|
PLUMBING FINAL
All fixtures must be in place. |
FAILED |
|
PLUMBING FINAL
All fixtures must be in place. |
SCHEDULED |
|
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
FAILED |
|
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
SCHEDULED |
|
FINAL
Final Approval as per requirements on plans. |
SCHEDULED |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)