BP131616 - 352 Units 101/201/202 Westwood Road, BLDG 2, (Inspection Only Permit)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP131616 - 352 Units 101/201/202 Westwood Road, BLDG 2, (Inspection Only Permit) | |
|---|---|
| Neighbourhood: | Westwood |
| Street Address: | 352 Units 101/201/202 Westwood Road, BLDG 2, (Inspection Only Permit) |
| Type of Application: | Commercial / Multi / Industrial |
| File Number: | BP131616 |
| Date Application Submitted: | February 28, 2026 |
| Application Description: |
New construction of three-storey, slab-on-grade Triplex. Building Classification: BCBC 2024, Part 9 building (Group C) residential, sprinklered, combustible construction. Building area: Building 2 (#352 Units 101/201/202) is 121.39 m², GFA 368.09 m². BP131615: Building 1 (350 WESTWOOD ROAD) - 187.48 m² GFA BP131616: Building 2 (352 Units 101/201/202 WESTWOOD ROAD) - 368.09 m² GFA 2026-SEP-16 REVISION: Multiple changes on both buildings. See approved plans. |
| Application Status: | ACTIVE |
| Builder: | MCNAUGHT CONTRACTING LTD |
| Issued Date: | July 31, 2026 |
| Expiry Date: | July 31, 2028 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 201 352 WESTWOOD ROAD | Property Report | |
| 101 352 WESTWOOD ROAD | Property Report | |
| 202 352 WESTWOOD ROAD | Property Report | |
| 350 WESTWOOD ROAD | R5 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
EXCAVATION
Excavation of soil, prior to placing forms. |
PASSED |
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
FAILED |
|
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
|
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PARTIAL |
|
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
|
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
|
UNDERSLAB RADON
Inspection of granular layer and piping |
PASSED |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)