BP131564 - 118-50 Tenth Street, (Cloverdale Paint)

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP131564 - 118-50 Tenth Street, (Cloverdale Paint)
Neighbourhood: Harewood    
Street Address: 118-50 Tenth Street, (Cloverdale Paint)
Type of Application: Commercial / Multi-Res Alteration
File Number: BP131564
Date Application Submitted: February 11, 2026
Application Description: Tenant improvements for unit 118 (Cloverdale Paint) - Change of use from Group A2 to Group E, Floor area: 396 m². Work includes updated interior layout, enlarged rear receiving door, removal of 2 showers, accessibility upgrades for one universal washroom, addition of 2 sinks for new utility and staff rooms, new fire suppression and mechanical ductwork throughout, upgrades to existing fire alarm system. No changes to fire separations proposed.

Exisitng Building Classification (BP113363): 2006 BCBC Group E 3.2.2.62 combustible and non-combustible sprinklered building with fire alarm, separated from adjacent connected building by 4-hr FRR Firewall. 2-hr FRR/FS existing between adjacent suite. Building area 1492 m2.

Revision 2026-AUG-07: Updated ceiling plan, mechanical, plumbing, sprinkler and lighting layouts, water line added to front of building for coffee maker.
Application Status: ACTIVE
Permit Value: $160,000.00
Issued Date: July 06, 2026
Expiry Date: July 06, 2028

Associated Properties

Address Zone More
50 TENTH STREET CC3 Property Report

Process Steps

Task Status
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

FAILED
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

FAILED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

CANCELLED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

CANCELLED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.