BP131084 - 309 Elizabeth Street (Building A)

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP131084 - 309 Elizabeth Street (Building A)
Neighbourhood: University District    
Street Address: 309 Elizabeth Street (Building A)
Type of Application: Single / Two Family Dwelling
File Number: BP131084
Date Application Submitted: July 28, 2025
Application Description: New construction of a 3-storey detached duplex on slab on grade on a residential R5-zoned lot.

Building Classification: BCBC 2024, Part 9 building (Group C) residential, unsprinklered, combustible construction. Building area: Unit A (309 Elizabeth Street ) is 74.61 m² and Unit B (269 CRAIG STREET) is 74.61 m², Total building area-149.22 m². Total GFA 316.50 m².
Building A ((309 Elizabeth Street )- 158.25 GFA
Building B (269 CRAIG STREET)- 158.25 GFA

Pad footing added. Location of fireplace changed. Length of engineered beam increased. Window in hutch deleted. Window sizes in all bedrooms changed.
Application Status: ACTIVE
Permit Value: $360,659.66
Building Area: 158.25 M2
1,703.39 ft2
Builder: MICHAEL PARKER CONSTRUCTION LTD
Issued Date: October 03, 2025
Expiry Date: October 03, 2027

Associated Properties

Address Zone More
309 ELIZABETH STREET R5 Property Report
309 ELIZABETH STREET Property Report

Process Steps

Task Status
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

PARTIAL
FOOTING / FORMS

Inspection of forms prior to any concrete being poured

PASSED
PERIMETER DRAIN

For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering

PARTIAL
PERIMETER DRAIN

For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering

PARTIAL
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible

PARTIAL
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete

PASSED
SANITARY CONNECTION

Pipe and Connection must be visible for inspection

PARTIAL
SANITARY CONNECTION

Pipe and Connection must be visible for inspection

PASSED
WATER CONNECTION

Pipe and Connection must be visable for inspection

PARTIAL
UNDERSLAB RADON

Inspection of granular layer and piping

PASSED
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.