BP130940 - 6043 Hammond Bay Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP130940 - 6043 Hammond Bay Road | |
|---|---|
| Neighbourhood: | Rutherford |
| Street Address: | 6043 Hammond Bay Road |
| Type of Application: | Single / Two Family Dwelling |
| File Number: | BP130940 |
| Date Application Submitted: | May 19, 2025 |
| Application Description: |
New 2-storey single-family dwelling with storage garage on R5 lot (House B). Second SFD development. House A (BP010783) GFA is116.10 m². Second Dwelling (BP130940) GFA is 190.17 m². |
| Application Status: | ACTIVE |
| Permit Value: | $443,457.91 |
| Building Area: |
193.90 M2 2,087.12 ft2 |
| Issued Date: | August 01, 2025 |
| Expiry Date: | August 01, 2027 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 6041 HAMMOND BAY ROAD | R5 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
EXCAVATION
Excavation of soil, prior to placing forms. |
PASSED |
|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PARTIAL |
|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
|
PERIMETER DRAIN
For perimeter drain , foundation walls should be damp proofed and drain tile in place with drain rock covering |
PASSED |
|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible |
PASSED |
|
STORM CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
|
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
PASSED |
|
WATER CONNECTION
Pipe and Connection must be visable for inspection |
PASSED |
|
UNDERSLAB RADON
Inspection of granular layer and piping |
PASSED |
|
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
FAILED |
|
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PASSED |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)