BP130520 - 5960-A Breonna Drive

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP130520 - 5960-A Breonna Drive
Neighbourhood: North Slope    
Street Address: 5960-A Breonna Drive
Type of Application: Accessory Building
File Number: BP130520
Date Application Submitted: December 12, 2024
Application Description: Construct two storey carriage house
Application Status: ACTIVE
Permit Value: $250,000.00
Building Area: 88.84 M2
956.26 ft2
Builder: CHIORANDO HOMES INC
Issued Date: January 24, 2025
Expiry Date: January 24, 2027

Associated Properties

Address Zone More
5960 BREONNA DRIVE R5 Property Report

Process Steps

Task Status
FOOTING/FORMS

Inspection of Forms prior to any concrete being poured for footing inspection. Forms must be complete and approved plans (complete with City Stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of Forms prior to any concrete being poured for footing inspection. Forms must be complete and approved plans (complete with City Stamp) must be onsite.

PASSED
UNDERSLAB RADON

Inspection of granular layer and piping

PASSED
UNDERSLAB RADON

Inspection of granular layer and piping

SCHEDULED
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible.

PASSED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

FAILED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PASSED
SANITARY CONNECTION

Pipe and Connection must be visible for inspection.

PARTIAL
SANITARY CONNECTION

Pipe and Connection must be visible for inspection.

PASSED
WATER CONNECTION

Pipe and connection must be visible for inspection.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

PARTIAL
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

FAILED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

FAILED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

FAILED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.