BP130341 - 764 Townsite Road (lower) 759 Begbie Street (upper), House A (INSPECTION ONLY)

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP130341 - 764 Townsite Road (lower) 759 Begbie Street (upper), House A (INSPECTION ONLY)
Neighbourhood: Townsite    
Street Address: 764 Townsite Road (lower) 759 Begbie Street (upper), House A (INSPECTION ONLY)
Type of Application: Commercial / Multi / Industrial
File Number: BP130341
Date Application Submitted: August 27, 2024
Application Description: New Construction of 2, 2 storey, 2 unit residential buildings BCBC Part 9, 109 m2 building area, combustible construction sprinklered to NFPA 13D. (House A)

1 Hr FRR/FS provided for floor assembly between units. 45min FRR/FS required between units.

BP130298 Main permit
BP130342 House B
Application Status: ACTIVE
Permit Value: $400,000.00
Builder: COASTAL SQUARE HOMES INC
Issued Date: March 06, 2025
Expiry Date: March 06, 2027

Associated Properties

Address Zone More
759 BEGBIE STREET Property Report
762 TOWNSITE ROAD R5 Property Report
764 TOWNSITE ROAD Property Report

Process Steps

Task Status
EXCAVATION

Excavation of soil, prior to placing forms.

CANCELLED
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PASSED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PASSED
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
LATERAL BRACING & SHEATHING

All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors.

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

CANCELLED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

CANCELLED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

FAILED
INTERIOR BRACED WALL PANELS

The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound.

PASSED
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.