BP130203 - 2232 Rosstown Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP130203 - 2232 Rosstown Road | |
---|---|
Neighbourhood: | Diver Lake |
Street Address: | 2232 Rosstown Road |
Type of Application: | Single / Two Family Alteration |
File Number: | BP130203 |
Date Application Submitted: | July 22, 2024 |
Application Description: | Single-storey addition over heated crawlspace and enclose part of existing veranda |
Application Status: | ACTIVE |
Permit Value: | $108,669.60 |
Building Area: |
47.94 M2 516.02 ft2 |
Issued Date: | September 24, 2024 |
Expiry Date: | September 24, 2026 |
Associated Properties
Address | Zone | More |
---|---|---|
2232 ROSSTOWN ROAD | R5 | Property Report |
Process Steps
Task | Status |
---|---|
EXCAVATION
Excavation of soil, prior to placing forms. |
PASSED |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PASSED |
UNDERSLAB RADON
Inspection of granular layer and piping |
PASSED |
ROUGH IN PLUMBING
Rough In plumbing must be complete including water piping. |
PASSED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PARTIAL |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. |
SCHEDULED |
INTERIOR BRACED WALL PANELS
The location of interior braced wall panels to be clearly indicated. This inspection is to take place prior to the installation of tape and joint compound. |
PASSED |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.