BP129890 - 104-2517 Bowen Road

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP129890 - 104-2517 Bowen Road
Neighbourhood: Diver Lake    
Street Address: 104-2517 Bowen Road
Type of Application: Commercial / Multi-Res Alteration
File Number: BP129890
Date Application Submitted: February 24, 2024
Application Description: Combining two commercial rental units (104 &102) into1 CRU (2485 m2) - base building landlord work, work includes alteration of demising wall to combine units, changes to fire alarm and sprinkler systems, existing plumbing capped, 1 washroom to remain
Future tenant improvement building permit required to occupy new enlarged space.

Sept 5/24 - revision for required upgrading of FRR/FS of existing demising walls

Existing 3.2.2.64 Group E building, 4225 m2, sprinklered with fire alarm, non-combustible construction
Application Status: COMPLETED
Permit Value: $300,000.00
Issued Date: June 11, 2024
File Close Date: December 12, 2024
Expiry Date: June 11, 2026

Associated Properties

Address Zone More
2517 BOWEN ROAD COR3 Property Report

Process Steps

Task Status
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

MONITORED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

CANCELLED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

FAILED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL

All fixtures must be in place.

CANCELLED
PLUMBING FINAL

All fixtures must be in place.

PASSED
APPROVAL-FIRE

Approval required prior to Occupancy

APPROVED
FINAL

Final approval as per requirements on plans.

FAILED
FINAL

Final approval as per requirements on plans.

PASSED

2024-12-12

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.