BP129842 - 202-4851 Cedar Ridge Place (Kinsu Chocolates)

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP129842 - 202-4851 Cedar Ridge Place (Kinsu Chocolates)
Neighbourhood: Rutherford    
Street Address: 202-4851 Cedar Ridge Place (Kinsu Chocolates)
Type of Application: Commercial / Multi-Res Alteration
File Number: BP129842
Date Application Submitted: January 22, 2024
Application Description: (Kinsu Chocolates) First occupancy of CRU shell space for a (Low A2) Group D occupancy. Floor area 91.75 m2. Work consists of interior partition walls, relocating 3 and adding 4 sprinkler heads, completing accessible washroom, adding 2 sinks, 2 pot-fillers, dishwasher and HWT. Occupant load of dining and staff 10 persons total.

Existing Building classification: BCBC 2018 Group D 3.2.2.63/ Group E 3.2.2.69, 183.5 m2 building area, combustible, sprinklered including attic space with Fire Alarm System. 1 hr FRR/FS Floor/roof assembly, 1 hr FRR/FS between suites. Total GFA is 367 m2.
Application Status: COMPLETED
Permit Value: $160,000.00
Builder: SHINING KNIGHT CONSTRUCTION INC
Issued Date: May 03, 2024
File Close Date: October 11, 2024
Expiry Date: May 03, 2026

Associated Properties

Address Zone More
4851 CEDAR RIDGE PLACE COR2 Property Report

Process Steps

Task Status
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL

All fixtures must be in place.

FAILED
PLUMBING FINAL

All fixtures must be in place.

PASSED
APPROVAL-VIHA

Approval required prior to Occupancy

APPROVED
OCCUPANCY FAILED
OCCUPANCY PASSED

2024-10-11

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.