BP129842 - 202-4851 Cedar Ridge Place (Kinsu Chocolates)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP129842 - 202-4851 Cedar Ridge Place (Kinsu Chocolates) | |
|---|---|
| Neighbourhood: | Rutherford |
| Street Address: | 202-4851 Cedar Ridge Place (Kinsu Chocolates) |
| Type of Application: | Commercial / Multi-Res Alteration |
| File Number: | BP129842 |
| Date Application Submitted: | January 22, 2024 |
| Application Description: |
(Kinsu Chocolates) First occupancy of CRU shell space for a (Low A2) Group D occupancy. Floor area 91.75 m2. Work consists of interior partition walls, relocating 3 and adding 4 sprinkler heads, completing accessible washroom, adding 2 sinks, 2 pot-fillers, dishwasher and HWT. Occupant load of dining and staff 10 persons total. Existing Building classification: BCBC 2018 Group D 3.2.2.63/ Group E 3.2.2.69, 183.5 m2 building area, combustible, sprinklered including attic space with Fire Alarm System. 1 hr FRR/FS Floor/roof assembly, 1 hr FRR/FS between suites. Total GFA is 367 m2. |
| Application Status: | COMPLETED |
| Permit Value: | $160,000.00 |
| Builder: | SHINING KNIGHT CONSTRUCTION INC |
| Issued Date: | May 03, 2024 |
| File Close Date: | October 11, 2024 |
| Expiry Date: | May 03, 2026 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 4851 CEDAR RIDGE PLACE | COR2 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
|
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
|
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
PASSED |
|
PLUMBING FINAL
All fixtures must be in place. |
FAILED |
|
PLUMBING FINAL
All fixtures must be in place. |
PASSED |
|
APPROVAL-VIHA
Approval required prior to Occupancy |
APPROVED |
| OCCUPANCY | FAILED |
| OCCUPANCY |
PASSED
2024-10-11 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)