BP129577 - 6374 Metral Drive (VIREB)

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP129577 - 6374 Metral Drive (VIREB)
Neighbourhood: Pleasant Valley    
Street Address: 6374 Metral Drive (VIREB)
Type of Application: Commercial / Multi-Res Alteration
File Number: BP129577
Date Application Submitted: September 26, 2023
Application Description: (Vancouver Island Real Estate Board VIREB) Interior renovations to the singular suite within the building, including new offices, staff kitchen, coffee room, exit and emergency lights, addition of 2 and relocation of 9 sprinkler heads. Doors and interior accessible routes to CSA B651-12.

Existing Building Classification (BP042804): BCBC 1992 Group D 3.2.2.39. (BCBC 2018 3.2.2.63.), 1015 m2 building area, one storey w/ basement, facing one street, combustible and noncombustible construction, sprinklered to NFPA 13-1989, with fire alarm. 45-min FRR/FS floors, 45-min FRR for combustible (no FRR for noncombustible) loadbearing walls/columns arches.
Application Status: COMPLETED
Permit Value: $450,000.00
Builder: CALJOUW CONTRACTING LTD
Issued Date: March 26, 2024
File Close Date: December 20, 2024
Expiry Date: March 26, 2026

Associated Properties

Address Zone More
6374 METRAL DRIVE CC4 Property Report

Process Steps

Task Status
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

FAILED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL

All fixtures must be in place.

FAILED
PLUMBING FINAL

All fixtures must be in place.

FAILED
PLUMBING FINAL

All fixtures must be in place.

PASSED
APPROVAL-FIRE

Approval required prior to Occupancy

APPROVED
FINAL

Final approval as per requirements on plans.

CANCELLED
FINAL

Final approval as per requirements on plans.

FAILED
FINAL

Final approval as per requirements on plans.

CANCELLED
FINAL

Final approval as per requirements on plans.

PASSED

2024-12-20

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.