BP129518 - 113-50 Tenth Street (Connect Hearing)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search Again| BP129518 - 113-50 Tenth Street (Connect Hearing) | |
|---|---|
| Neighbourhood: | Harewood |
| Street Address: | 113-50 Tenth Street (Connect Hearing) |
| Type of Application: | Leasehold Improvements |
| File Number: | BP129518 |
| Date Application Submitted: | August 29, 2023 |
| Application Description: |
Tenant Improvements:(Connect Hearing) 3.2.2.61. Group D (personal services), located in Building 3, Construct interior partition walls, Relocate 6 sprinkler heads and add 6 new sprinkler heads to existing NFPA 13 sprinkler system, install wash basin and toilet to finish existing accessible bathroom rough in and add two new sinks, Unit Area is 113.64m². Existing building is divided by two firewalls into three buildings. All buildings are combustible construction with fire alarm system. 1st building (East End): Pharmacy Group E/A2, BCBC 2006 3.2.2.27/3.2.2.62, 1489 m², sprinklered. 2nd building (Centre): Group E/A2 , BCBC 2018 3.2.2.68/3.2.2.28, 794 m², unsprinklered. 3rd building (West End): Group D/E, BCBC 2012 3.2.2.61/3.2.2.67, 1379m², sprinklered. |
| Application Status: | COMPLETED |
| Permit Value: | $200,000.00 |
| Builder: | TERRY MCCARTAN CONTRACTING |
| Issued Date: | January 09, 2024 |
| File Close Date: | March 05, 2024 |
| Expiry Date: | January 09, 2026 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 50 TENTH STREET | CC3 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PARTIAL |
|
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PASSED |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visible for inspection. |
PARTIAL |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visible for inspection. |
PASSED |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PASSED |
|
PLUMBING FINAL
All fixtures must be in place. |
PASSED |
|
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
PASSED |
|
FINAL
Final Approval as per requirements on plans. |
FAILED |
|
FINAL
Final Approval as per requirements on plans. |
PASSED
2024-03-05 |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.