BP129365 - 5690 Edgewater Lane (BLDG B) - (LAND: 4775 Uplands Drive)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP129365 - 5690 Edgewater Lane (BLDG B) - (LAND: 4775 Uplands Drive) | |
---|---|
Neighbourhood: | Rutherford |
Street Address: | 5690 Edgewater Lane (BLDG B) - (LAND: 4775 Uplands Drive) |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP129365 |
Date Application Submitted: | June 16, 2023 |
Application Description: |
5690 Edgewater Lane (BLDG B) Construction of a new 48 unit apartment building, Group C, 3.2.2.51, 4 storey, fire alarm, sprinklered throughout, standpipes in exits. 2030.15 m2 Parking Garage classification as group F3, 3.2.2.82. Building area for code purposes for building is 1141.2 m2. Key FS /FRR are 1 Hour FS/FRR between residential suites, public corridor, floor assemblies, upper floor at ceiling and loadbearing supports. 1.5 hrs FS/FRR in Parkade between occupancies. Storage rooms, exit stairs, elevators and machine room; all doors in fire separations to be self-closing with positive latching mechanisms. Total GFA 6904.94 m2. SEPARATE PERMITS: 5680 Edgewater Lane BLDG A: BP129364 - AMENITY PAVILION INSPECTION ONLY: BP130003 REVISION 2024-NOV-06: Reduce retaining wall heights to 1.2m by adding additional walls. REVISION 2025-JUN-20: See internal notes. |
Application Status: | ACTIVE |
Permit Value: | $15,000,000.00 |
Builder: | WESTMARK CONSTRUCTION LTD |
Issued Date: | June 19, 2024 |
Expiry Date: | June 19, 2026 |
Associated Properties
Address | Zone | More |
---|---|---|
101 5690 EDGEWATER LANE | Property Report | |
4775 UPLANDS DRIVE | R8 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PARTIAL |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PARTIAL |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PASSED |
STORM CONNECTION
Pipe and connection must be visible for inspection. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
FAILED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
CANCELLED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
FAILED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
MONITORED |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.