BP129086 - 115-50 Tenth Street
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP129086 - 115-50 Tenth Street | |
---|---|
Neighbourhood: | Harewood |
Street Address: | 115-50 Tenth Street |
Type of Application: | Commercial / Multi-Res Alteration |
File Number: | BP129086 |
Date Application Submitted: | February 23, 2023 |
Application Description: |
Commercial Alteration: Combine Units 114A and 115 into a single shell suite. Create new common use electrical room with separate exterior access door, landing and stairs.1-hr FRR demising wall required. Rough-in plumbing including underslab for one tenant washroom and two dog wash stations. Remove two existing washrooms and previously installed grease interceptor and cap abandoned plumbing. Existing Unit 115: shell Group E, 190.5 m2, Existing Unit 114A: Group E, 206.71 m2, = 402.46m2 CRU Unit 115: 3.2.2.68 Group E shell 402.46 m2, located in Building 2. 2023-DEC-12 REVISION: Relocate water service and delete booster pump. Building 2 (Centre): Group E/A2, BCBC 2018 3.2.2.68/3.2.2.28, 794 m2 building area, combustible construction, fire alarm, unsprinklered. |
Application Status: | COMPLETED |
Permit Value: | $70,000.00 |
Issued Date: | September 22, 2023 |
File Close Date: | December 18, 2023 |
Expiry Date: | September 22, 2025 |
Associated Properties
Address | Zone | More |
---|---|---|
50 TENTH STREET | CC3 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
CANCELLED |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
CANCELLED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
CANCELLED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
PLUMBING FINAL
All fixtures must be in place. |
PASSED |
FINAL
Final approval as per requirements on plans. |
FAILED |
FINAL
Final approval as per requirements on plans. |
PASSED
2023-12-18 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.