BP128951 - 1200 Dufferin Crescent (NRGH CT Scanner)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP128951 - 1200 Dufferin Crescent (NRGH CT Scanner) | |
---|---|
Neighbourhood: | Townsite |
Street Address: | 1200 Dufferin Crescent (NRGH CT Scanner) |
Type of Application: | Commercial / Multi-Res Alteration |
File Number: | BP128951 |
Date Application Submitted: | December 22, 2022 |
Application Description: |
NRGH SPECT-CT Scan facility renovation, work includes - removing existing partition walls, relocating 2 washrooms & 2 sinks and constructing new interior partition walls. Building Classification : BCBC2012 - 3.2.2.38 /3.2.6, non combustible construction, sprinklered with fire alarm. Major occupancy B-2 with subsidiary occupancies. Jul 17/24 - Revision: updated structural drawings received |
Application Status: | COMPLETED |
Permit Value: | $700,000.00 |
Issued Date: | June 13, 2023 |
File Close Date: | July 29, 2024 |
Expiry Date: | June 13, 2025 |
Associated Properties
Address | Zone | More |
---|---|---|
1200 DUFFERIN CRESCENT | CS1 | Property Report |
Process Steps
Task | Status |
---|---|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
CANCELLED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
MONITORED |
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
FAILED |
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
CANCELLED |
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
PASSED |
PLUMBING FINAL
All fixtures must be in place. |
FAILED |
PLUMBING FINAL
All fixtures must be in place. |
CANCELLED |
PLUMBING FINAL
All fixtures must be in place. |
PASSED |
FINAL
Final approval as per requirements on plans. |
CANCELLED |
FINAL
Final approval as per requirements on plans. |
CANCELLED |
FINAL
Final approval as per requirements on plans. |
CANCELLED |
FINAL
Final approval as per requirements on plans. |
CANCELLED |
FINAL
Final approval as per requirements on plans. |
CANCELLED |
FINAL
Final approval as per requirements on plans. |
FAILED |
FINAL
Final approval as per requirements on plans. |
PASSED
2024-07-29 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.