BP128917 - F2-6631 Island Highway North (Pho 11 Noodle Bar)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP128917 - F2-6631 Island Highway North (Pho 11 Noodle Bar) | |
---|---|
Neighbourhood: | Dover |
Street Address: | F2-6631 Island Highway North (Pho 11 Noodle Bar) |
Type of Application: | Leasehold Improvements |
File Number: | BP128917 |
Date Application Submitted: | December 03, 2022 |
Application Description: |
Pho11 Noodle Bar - 29.7 m2 suite in the food court. Work includes adding partition walls, NFPA 96 hood and plumbing fixtures, no changes to existing sprinkler system. Apr 3/23: Revision - revised plumbing isometric drawings Woodgrove Mall, Group E building, BCBC 2012 3.2.2.62, sprinkled, noncombustible, fire alarm. |
Application Status: | COMPLETED |
Permit Value: | $50,000.00 |
Builder: | ALEX K CONSTRUCTION |
Issued Date: | February 16, 2023 |
File Close Date: | April 25, 2023 |
Expiry Date: | February 16, 2025 |
Associated Properties
Address | Zone | More |
---|---|---|
6631 ISLAND HIGHWAY N | CC4 | Property Report |
Process Steps
Task | Status |
---|---|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
CANCELLED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
CANCELLED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PASSED |
PLUMBING FINAL
All fixtures must be in place. |
FAILED |
PLUMBING FINAL
All fixtures must be in place. |
FAILED |
PLUMBING FINAL
All fixtures must be in place. |
FAILED |
PLUMBING FINAL
All fixtures must be in place. |
PASSED |
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
FAILED |
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
FAILED |
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
PASSED |
APPROVAL-FIRE
Approval required prior to Occupancy |
APPROVED |
APPROVAL-VIHA
Approval required prior to Occupancy |
APPROVED |
FINAL
Final Approval as per requirements on plans. |
CANCELLED |
FINAL
Final Approval as per requirements on plans. |
FAILED |
FINAL
Final Approval as per requirements on plans. |
CANCELLED |
FINAL
Final Approval as per requirements on plans. |
CANCELLED |
FINAL
Final Approval as per requirements on plans. |
PASSED
2023-04-25 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.