Application Description: |
Commercial Alteration: Unit #101,(Tablet Pharmacy) Floor Area 113.82 m2. Change of use of CRU from Group A2 to Group E for new retail space including one accessible washroom, one HWT and one double sink; and completion of sprinklers below suspended ceiling (12 Pendant heads); accessible remote door opener and one relocated pull station. BCBC 2018 classified as Group A2 - 3.2.2.27 / Group E - 3.2.2.63 Occupancy, Building Area 496m2, combustible/ noncombustible construction, sprinklered with fire alarm system. 2 hr FRR F/S demising walls between each unit. |
Application Status: | COMPLETED |
Permit Value: | $25,000.00 |
Issued Date: | January 13, 2023 |
File Close Date: | August 14, 2023 |
Expiry Date: | January 13, 2025 |
Associated Properties
Address | Zone | More |
---|---|---|
6361 HAMMOND BAY ROAD | CC4 | Property Report |
Process Steps
Task | Status |
---|---|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
FAILED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
FAILED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
FAILED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
PASSED |
PLUMBING FINAL
All fixtures must be in place. |
FAILED |
PLUMBING FINAL
All fixtures must be in place. |
FAILED |
PLUMBING FINAL
All fixtures must be in place. |
PASSED |
APPROVAL-FIRE
Approval required prior to Occupancy |
APPROVED |
OCCUPANCY |
PASSED
2023-08-14 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.