BP128556 - 6 -1611 Bowen Road (Maxx Insurance)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP128556 - 6 -1611 Bowen Road (Maxx Insurance) | |
---|---|
Neighbourhood: | Northfield |
Street Address: | 6 -1611 Bowen Road (Maxx Insurance) |
Type of Application: | Commercial / Multi-Res Alteration |
File Number: | BP128556 |
Date Application Submitted: | June 21, 2022 |
Application Description: |
"Change of use" from Group E to Group D. Unit 6 (Maxx Insurance). Work includes installation of one additional universal washroom and new office partitions. Suite area 117m2. 2 existing exits. Max travel distance 40m. Max occupant load 10 people based single universal washroom. Minimum 45min FRR/FS required to be maintained to exits, floor/ceiling and supporting structures. Existing building classification; 2006 BCBC 3.2.2.55 Group D, 776.6m2, two storey, combustible or non-combustible, unsprinklered, minimum 45min FRR/FS required for exits, floors and supporting assemblies. 1hr FRR/FS currently provided between Units 5/6/exits, and Units 3/6. REVISION: 2023-MAR-22 - remove walls, remove existing washroom and reduce occupant load to 10. REVISION 2023-MAY-10 - add office partitions. |
Application Status: | COMPLETED |
Builder: | FISK CONSTRUCTION INC |
Issued Date: | January 25, 2023 |
File Close Date: | July 28, 2023 |
Expiry Date: | January 25, 2025 |
Associated Properties
Address | Zone | More |
---|---|---|
1611 BOWEN ROAD | COR3 | Property Report |
Process Steps
Task | Status |
---|---|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
PLUMBING FINAL
All fixtures must be in place. |
PASSED |
FINAL
Final approval as per requirements on plans. |
PASSED
2023-07-28 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.