| Application Description: |
New construction of single-family dwelling REVISION 2026-JUN-09: Added Fire Suppression Engineer for service main sizing change |
| Application Status: | ACTIVE |
| Permit Value: | $228,709.65 |
| Building Area: |
88.05 M2 947.76 ft2 |
| Issued Date: | December 21, 2022 |
| Expiry Date: | December 20, 2026 |
Associated Properties
| Address | Zone | More |
|---|---|---|
| 121 PIRATES LANE | R3 | Property Report |
Process Steps
| Task | Status |
|---|---|
|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
CANCELLED |
|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PARTIAL |
|
FOOTING / FORMS
Inspection of forms prior to any concrete being poured |
PASSED |
|
SANITARY CONNECTION
Pipe and Connection must be visible for inspection |
PARTIAL |
|
WATER CONNECTION
Pipe and Connection must be visable for inspection |
PARTIAL |
|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping |
PASSED |
|
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection |
FAILED |
|
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
CANCELLED |
|
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
|
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate & Truss Layouts required for approval |
FAILED |
|
INSULATION
Insulation and vapour barrier to be complete prior to inspection |
PARTIAL |
| Map |
|---|
View in Google Earth (KML)
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

View in Google Earth (KML)