BP128081 - 263/265/267/269 Hansen Road (Parent: 200 Hansen Road) (BLOCK 12)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP128081 - 263/265/267/269 Hansen Road (Parent: 200 Hansen Road) (BLOCK 12) | |
---|---|
Neighbourhood: | Northfield |
Street Address: | 263/265/267/269 Hansen Road (Parent: 200 Hansen Road) (BLOCK 12) |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP128081 |
Date Application Submitted: | December 07, 2021 |
Application Description: |
Units 263/265/267/269 - New construction of 3 storey, 4 unit multi-family, row housing. Building Classification: BCBC 2018 Group C (Residential), Part 9, 270.02m2 building area, combustible construction, sprinklered NFPA13R. 1HR FRR/FS, and 57 STC for demising walls. Total GFA is 784.89m2. Phase 1 of development is 49 units in 15 buildings, and 1 community utility building. |
Application Status: | ACTIVE |
Permit Value: | $1,507,798.33 |
Builder: | 1303320 BC LTD |
Issued Date: | June 15, 2023 |
Expiry Date: | June 15, 2025 |
Associated Properties
Address | Zone | More |
---|---|---|
200 HANSEN ROAD | , R8 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
FIRELINE
Fireline for the sprinkler system must be complete and visable for inspection. |
PASSED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PASSED |
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.