BP127935 - 341 Irwin Street (Caged Athletics)
Neighbourhood: South End    
Street Address: 341 Irwin Street (Caged Athletics)
Type of Application: Commercial / Multi-Res Alteration
File Number: BP127935
Date Application Submitted: November 07, 2021
Application Description: (Caged Athletics) Change of building major occupancy. from Group F2 to Group D (Low A2).

New building classification; BCBC 2018 BCBC 3.2.2.63 (Group D). Single storey, combustible or non-combustible construction sprinklered to NFPA13 with fire alarm system. 562m2 building area. 2 universal washrooms. Posted maximum occupant load of 30. 568.9m2 GFA.

2023-NOV-08 REVISION: to add water entry service room and change structural EOR.
Application Status: HOLDBACK
Permit Value: $200,000.00
Building Area: 562.00 M2
6,049.31 ft2
Issued Date: April 28, 2023
File Close Date: November 24, 2023
Expiry Date: April 28, 2025

Associated Properties

Address Zone More
341 IRWIN STREET COR3 Property Report

Process Steps

Task Status
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PASSED
STORM CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
STORM CONNECTION

Pipe and connection must be visible for inspection.

PASSED
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PASSED
WATER CONNECTION

Pipe Connection must be visible for inspection.

PARTIAL
WATER CONNECTION

Pipe Connection must be visible for inspection.

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

FAILED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

FAILED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL

All fixtures must be in place.

FAILED
PLUMBING FINAL

All fixtures must be in place.

PASSED
APPROVAL-ENGINEERING

Approval required prior to Occupancy

APPROVED
APPROVAL-FIRE

Approval required prior to Occupancy

APPROVED
OCCUPANCY FAILED
FINAL

Final approval as per requirements on plans.

PASSED

2023-11-24

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy