BP127822 - 929 Hecate Street (daycare/multi-family)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP127822 - 929 Hecate Street (daycare/multi-family) | |
---|---|
Neighbourhood: | Downtown/Old City |
Street Address: | 929 Hecate Street (daycare/multi-family) |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP127822 |
Date Application Submitted: | September 01, 2021 |
Application Description: |
Construction of a 2 storey commercial/ multifamily building. Building Classification: Group A2 3.2.2.25 (Daycare) and Group C 3.2.2.53 (Residential). Un-sprinklered, combustible building with fire alarm system. 211.27 m2 building area. 1 hour FRR/FS required between units and exit stair and 45 min FRR required for all loadbearing supports. North and South walls have a 1 hour FRR and non-combustible cladding. Concrete piles with grade beam foundation. Total GFA is: 413.16: Daycare area: 201.89 m2. Second floor multifamily units area: 211.27m2 2023-JUN-26 REVISION to revise foundation drawings. 2023-JUL-11 REVISION to add two emergency floor drains. 2023-AUG-15 REVISION change stair layout. 2023-SEP-12 REVISION change rear stair layout. |
Application Status: | COMPLETED |
Permit Value: | $1,200,000.00 |
Builder: | SAYWELL CONTRACTING LTD |
Issued Date: | August 02, 2022 |
File Close Date: | January 05, 2024 |
Expiry Date: | August 02, 2024 |
Associated Properties
Address | Zone | More |
---|---|---|
929 HECATE STREET | R14 | Property Report |
Process Steps
Task | Status |
---|---|
EXCAVATION
Excavation of soil, prior to placing forms. |
PARTIAL |
EXCAVATION
Excavation of soil, prior to placing forms. |
PASSED |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PARTIAL |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
CANCELLED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
FAILED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
CANCELLED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
PLUMBING FINAL
All fixtures must be in place. |
FAILED |
PLUMBING FINAL
All fixtures must be in place. |
FAILED |
PLUMBING FINAL
All fixtures must be in place. |
PASSED |
APPROVAL-ENGINEERING
Approval required prior to Occupancy |
APPROVED |
APPROVAL-FIRE
Approval required prior to Occupancy |
APPROVED |
OCCUPANCY | FAILED |
OCCUPANCY | FAILED |
OCCUPANCY | CANCELLED |
OCCUPANCY |
PASSED
2024-01-05 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.