BP127715 - 5000 Rheanna Place

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP127715 - 5000 Rheanna Place
Neighbourhood: Pleasant Valley    
Street Address: 5000 Rheanna Place
Type of Application: Single / Two Family Alteration
File Number: BP127715
Date Application Submitted: August 12, 2021
Application Description: Construction of two-storey addition including a secondary suite.

2021-NOV-08 REVISION: Added hot water tank, new attic access and new vault line in master bedroom
Application Status: COMPLETED
Permit Value: $225,000.00
Building Area: 41.10 M2
442.40 ft2
Issued Date: September 08, 2021
File Close Date: February 25, 2022
Expiry Date: September 08, 2023

Associated Properties

Address Zone More
5000 RHEANNA PLACE R1 Property Report

Process Steps

Task Status
EXCAVATION

Excavation of soil, prior to placing forms.

CANCELLED
EXCAVATION

Excavation of soil, prior to placing forms.

CANCELLED
EXCAVATION

Excavation of soil, prior to placing forms.

PASSED
FOOTING/FORMS

Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PASSED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

CANCELLED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PASSED
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible

FAILED
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible

PARTIAL
UNDERSLAB PLUMBING

Complete underslab plumbing must be visible

PASSED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PASSED
ROUGH IN PLUMBING

Rough In plumbing must be complete including water piping.

FAILED
ROUGH IN PLUMBING

Rough In plumbing must be complete including water piping.

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

FAILED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

FAILED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PASSED
FRAMING

Rough in plumbing & electrical must be complete.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection

PASSED
FINAL

Final approval as per requirements on plans.

FAILED
FINAL

Final approval as per requirements on plans.

PASSED

2022-02-25

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy