BP127699 - 1525 Cranberry Avenue (Inspection folder) 1503 (Parent)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP127699 - 1525 Cranberry Avenue (Inspection folder) 1503 (Parent) | |
---|---|
Neighbourhood: | Chase River |
Street Address: | 1525 Cranberry Avenue (Inspection folder) 1503 (Parent) |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP127699 |
Date Application Submitted: | July 16, 2021 |
Application Description: |
-For inspections only- Chase River Elementary- Construction of a Before and After School Care Modular Building. Building Classified as 2018 BCBC 3.2.2.28- Combustible or non combustible construction; sprinklered with fire alarm. -134m2 Plumbing work includes; Installation of 1 sink 3 wc and 3 Lavs. One Universal WC is proposed. |
Application Status: | COMPLETED |
Builder: | THE BOARD OF EDUCATION OF SCHOOL DISTRICT NO 68 (NANAIMO-LADYSMITH) |
Issued Date: | March 10, 2022 |
File Close Date: | August 08, 2023 |
Expiry Date: | March 10, 2024 |
Associated Properties
Address | Zone | More |
---|---|---|
1503 CRANBERRY AVENUE | CS1 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
FAILED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
FAILED |
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
PASSED |
PLUMBING FINAL
All fixtures must be in place. |
FAILED |
PLUMBING FINAL
All fixtures must be in place. |
PASSED |
APPROVAL-ENGINEERING
Approval required prior to Occupancy |
APPROVED |
APPROVAL-FIRE
Approval required prior to Occupancy |
APPROVED |
APPROVAL-VIHA
Approval required prior to Occupancy |
APPROVED |
OCCUPANCY | FAILED |
OCCUPANCY | FAILED |
OCCUPANCY |
PASSED
2023-08-08 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.