BP127339 - 102 - 6373 Hammond Bay (6361 Hammond Bay-parent)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP127339 - 102 - 6373 Hammond Bay (6361 Hammond Bay-parent) | |
---|---|
Neighbourhood: | Rutherford |
Street Address: | 102 - 6373 Hammond Bay (6361 Hammond Bay-parent) |
Type of Application: | Commercial / Multi-Res Alteration |
File Number: | BP127339 |
Date Application Submitted: | March 16, 2021 |
Application Description: |
(Bar Burrito) - UNIT 102 - Interior work to complete CRU for Group A2 (restaurant), 131.5 m2, Install NFPA 96 commercial hood fan c/w wet chemical suppression system, 2 accessible washrooms. Adding 2 and relocating 9 sprinkler heads. BCBC 2018 classified as 3.2.2.27. Group A2 Occupancy,496m2,combustible/ noncombustible construction, sprinklered with fire alarm system. 2 hr FRR F/S demising walls between each unit. |
Application Status: | COMPLETED |
Permit Value: | $100,000.00 |
Issued Date: | August 04, 2021 |
File Close Date: | July 18, 2022 |
Expiry Date: | August 04, 2023 |
Associated Properties
Address | Zone | More |
---|---|---|
6361 HAMMOND BAY ROAD | CC4 | Property Report |
Process Steps
Task | Status |
---|---|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PARTIAL |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
FAILED |
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
FAILED |
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
PASSED |
PLUMBING FINAL
All fixtures must be in place. |
FAILED |
PLUMBING FINAL
All fixtures must be in place. |
FAILED |
PLUMBING FINAL
All fixtures must be in place. |
PASSED |
APPROVAL-FIRE
Approval required prior to Occupancy |
APPROVED |
OCCUPANCY | FAILED |
OCCUPANCY | CANCELLED |
OCCUPANCY | FAILED |
OCCUPANCY |
PASSED
2022-07-18 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.