BP127337 - 5646 Big Bear Ridge
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP127337 - 5646 Big Bear Ridge | |
---|---|
Neighbourhood: | Pleasant Valley |
Street Address: | 5646 Big Bear Ridge |
Type of Application: | Accessory Building |
File Number: | BP127337 |
Date Application Submitted: | March 30, 2021 |
Application Description: | New foundation under relocated accessory building. Accessory building was built under BP110581. |
Application Status: | COMPLETED |
Permit Value: | $7,000.00 |
Building Area: |
26.75 M2 287.93 ft2 |
Issued Date: | May 28, 2021 |
File Close Date: | May 10, 2023 |
Expiry Date: | May 29, 2023 |
Associated Properties
Address | Zone | More |
---|---|---|
5646 BIG BEAR RIDGE | R5 | Property Report |
Process Steps
Task | Status |
---|---|
EXCAVATION
Excavation of soil, prior to placing forms. |
PASSED |
FOOTING/FORMS
Inspection of Forms prior to any concrete being poured for footing inspection. Forms must be complete and approved plans (complete with City Stamp) must be onsite. |
PASSED |
FOOTING/FORMS
Inspection of Forms prior to any concrete being poured for footing inspection. Forms must be complete and approved plans (complete with City Stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
FAILED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
FAILED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
CANCELLED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
FINAL
Final approval as per requirements on plans. |
FAILED |
FINAL
Final approval as per requirements on plans. |
FAILED |
FINAL
Final approval as per requirements on plans. |
PASSED
2023-05-10 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.