BP127227 - 104-525 Third Street(Bees Knees)

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP127227 - 104-525 Third Street(Bees Knees)
Neighbourhood: University District    
Street Address: 104-525 Third Street(Bees Knees)
Type of Application: Commercial / Multi-Res Alteration
File Number: BP127227
Date Application Submitted: March 02, 2021
Application Description: (Bees Knees) Unit #104 - "Change of Use" of CRU from Group E to Group D/Low A2 occupancy, 143.7 m2. Improvements include creating 2 accessible washrooms, kitchen sink, dishwasher, hand washing sink, mop-sink and HWT. Kitchen with commercial NFPA-96 exhaust hood c/w wet chemical suppression system. Installation of 9 additional pendant sprinkler heads.

2018 BCBC: 22 Strata unit residential apartment building with 5 commercial rental units on main floor and basement level. 794 m2, 4 storey, Group C 3.2.2.51, Group E 3.2.2.65, Group F3 3.2.2.84, Group D 3.2.2.59, Total area of all floors, including parking garage is 3634.4 m2. Sprinklered, Fire Alarm system, combustible and/or noncombustible construction. 1 hr. FS/F.R.R. is required between suites, suites and corridors/stairwells/elevator shaft and 1 hr. F.R.R. for floor assemblies, load-bearing walls and columns. Parking Garage is required to be separated from the remainder of the building by a 1.5 hrs. FS/F.R.R.
Application Status: COMPLETED
Permit Value: $75,000.00
Builder: SAYWELL CONTRACTING LTD
Issued Date: June 25, 2021
File Close Date: September 28, 2021
Expiry Date: June 26, 2023

Associated Properties

Address Zone More
104   525 THIRD STREET COR2 Property Report

Process Steps

Task Status
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

FAILED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL

All fixtures must be in place.

PASSED
APPROVAL-FIRE

Approval required prior to Occupancy

APPROVED
APPROVAL-VIHA

Approval required prior to Occupancy

APPROVED
OCCUPANCY FAILED
OCCUPANCY PASSED

2021-09-28

FINAL

Final approval as per requirements on plans.

CANCELLED
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.