BP126816 - 2050 Latimer Rd (Day Care)

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP126816 - 2050 Latimer Rd (Day Care)
Neighbourhood: Northfield    
Street Address: 2050 Latimer Rd (Day Care)
Type of Application: Commercial / Multi / Industrial
File Number: BP126816
Date Application Submitted: October 16, 2020
Application Description: Forest Park Elementary School - New Modular Bldg #1 for Childcare, (Day Care) Building Classification 3.2.2.28, Group A2 Occupancy(134 m2) Combustible construction, sprinklered with fire alarm. walls between portables built as a 1hr FRR/FS. Work includes new pier type foundations and site built stairs and ramps for access. Plumbing within the modules include 1 Universal WC; 3 additional toilets; 3 washbasins; 1 sink and 1 auto washer.

REVISION: SEP.13,2022-Change layout to M5
Application Status: COMPLETED
Permit Value: $77,036.27
Builder: THE BOARD OF EDUCATION OF SCHOOL DISTRICT NO 68 (NANAIMO-LADYSMITH)
Issued Date: November 12, 2021
File Close Date: November 01, 2022
Expiry Date: November 13, 2023

Associated Properties

Address Zone More
2050 LATIMER ROAD CS1 Property Report

Process Steps

Task Status
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PASSED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PASSED
FIRELINE

Fireline for the sprinkler system must be complete and visable for inspection.

PARTIAL
STORM CONNECTION

Pipe and connection must be visible for inspection.

PASSED
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PASSED
WATER CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
WATER CONNECTION

Pipe and connection must be visible for inspection.

PASSED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

CANCELLED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

FAILED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

CANCELLED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

FAILED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

FAILED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

CANCELLED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL

All fixtures must be in place.

FAILED
PLUMBING FINAL

All fixtures must be in place.

FAILED
PLUMBING FINAL

All fixtures must be in place.

PASSED
APPROVAL-ENGINEERING

Approval required prior to Occupancy

APPROVED
APPROVAL-FIRE

Approval required prior to Occupancy

APPROVED
APPROVAL-VIHA

Approval required prior to Occupancy

APPROVED
OCCUPANCY FAILED
OCCUPANCY PASSED

2022-11-01

FINAL

Final approval as per requirements on plans.

FAILED
FINAL

Final approval as per requirements on plans.

CANCELLED
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy