BP126677 - 1200 Dufferin Crescent (ICU)

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP126677 - 1200 Dufferin Crescent (ICU)
Neighbourhood: Townsite    
Street Address: 1200 Dufferin Crescent (ICU)
Type of Application: Commercial / Multi / Industrial
File Number: BP126677
Date Application Submitted: October 27, 2020
Application Description: (ACUTE CARE - ICU) New construction of a 2 Storey addition with basement to the NRGH. Building Area 1021.3 m2, Group B2, constructed to 3.2.2.38. Fire Alarm System, Sprinklers
GFA 2724.17 m2. F/S with 2 hour FRR between new addition and existing Hospital, and for Elevator shafts and stairwells. F/S with 1 hour FRR between wards on 3rd floor. F/S with 0 hour FRR between rooms on the 3rd floor. A separate building permit is required to develop the 2nd floor.

Alternative Solution for Exit Exposure Protection. Sprinkler heads located at: Level G - Glazing on North Elevation; Level 1 - Glazing in future HAU on North and South Elevations; Level 2 - Glazing in ICU on North and South Elevations.
Jun 13/23 - Revision: fitting out first floor previously identified as shell space, changing fire protection engineer of record, updating record drawings, building permit renewed
Application Status: ACTIVE
Permit Value: $33,230,000.00
Builder: STUART OLSON
Issued Date: January 06, 2021
Expiry Date: January 06, 2025

Associated Properties

Address Zone More
1200 DUFFERIN CRESCENT CS1 Property Report

Process Steps

Task Status
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PASSED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PASSED
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

CANCELLED
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PASSED
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

FAILED
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

FAILED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PARTIAL
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PASSED
STORM CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
STORM CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
STORM CONNECTION

Pipe and connection must be visible for inspection.

PASSED
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PASSED
WATER CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

CANCELLED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

FAILED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

PASSED
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

MONITORED
MONITORING FIELD REVIEW

A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional.

MONITORED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

FAILED
PLUMBING FINAL

All fixtures must be in place.

FAILED
PLUMBING FINAL

All fixtures must be in place.

FAILED
APPROVAL-ENGINEERING

Approval required prior to Occupancy

APPROVED
APPROVAL-FIRE

Approval required prior to Occupancy

IN-PROGRESS
APPROVAL-PLANNING

Approval required prior to Occupancy

APPROVED
OCCUPANCY FAILED
FINAL

Final approval as per requirements on plans.

CANCELLED
Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy