BP126457 - 109 Martinez Place
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP126457 - 109 Martinez Place | |
---|---|
Neighbourhood: | Rutherford |
Street Address: | 109 Martinez Place |
Type of Application: | Accessory Building |
File Number: | BP126457 |
Date Application Submitted: | June 22, 2020 |
Application Description: |
Single storey slab on grade carriage house with a mechanical room in the attic REVISION-2020-OCT-02: changed bathroom layout, windows. Spatial updated REVISION-2020-OCT-21: Add window to mechanical room. |
Application Status: | HOLDBACK |
Permit Value: | $155,231.94 |
Building Area: |
89.74 M2 965.95 ft2 |
Builder: | ISLAND RED CEDAR CONSTRUCTION LTD |
Issued Date: | August 11, 2020 |
File Close Date: | April 06, 2021 |
Expiry Date: | August 11, 2022 |
Associated Properties
Address | Zone | More |
---|---|---|
109 MARTINEZ PLACE | R1 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of Forms prior to any concrete being poured for footing inspection. Forms must be complete and approved plans (complete with City Stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PASSED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
FAILED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PASSED |
SANITARY CONNECTION
Pipe and Connection must be visible for inspection. |
PASSED |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
LATERAL BRACING & SHEATHING
All nailing and blocking associated with braced wall panels to be completed for this inspection. Wood-based interior braced wall panels to be sheathed. Exterior braced wall panel locations to be clearly marked out on the interior and exterior. Interior braced wall panels to be clearly marked so their location can be seen now and later at the time of INTERIOR BRACED WALL PANEL INSPECTION. Additional anchor bolts shall be installed two per braced wall panel where a building contains framed walls supporting more than two floors. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
INTERIOR BRACED WALL PANELS | PASSED |
OCCUPANCY
Occupancy inspection to be used for new accessory suite (Carriage House). Covenant must be registered on title, HPO in place, private outdoor space must be provided for occupants, one onsite parking spot |
FAILED |
OCCUPANCY
Occupancy inspection to be used for new accessory suite (Carriage House). Covenant must be registered on title, HPO in place, private outdoor space must be provided for occupants, one onsite parking spot |
PASSED
2021-04-06 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.