BP126007 - 250, 255 & 260 - 2000 Island Highway N
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP126007 - 250, 255 & 260 - 2000 Island Highway N | |
---|---|
Neighbourhood: | Departure Bay |
Street Address: | 250, 255 & 260 - 2000 Island Highway N |
Type of Application: | Commercial / Multi-Res Alteration |
File Number: | BP126007 |
Date Application Submitted: | November 27, 2019 |
Application Description: |
(Landlord Work) Return to shell space. Combine 2 adjacent units together into 1 larger unit, relocate alternate-solution fire wall under new alternative solution . Remove existing 3" mains and sprinkler water curtain and install new 3" mains and sprinkler water curtain at new firewall location. NOTE** All for future new tenant (Anytime Fitness- permit under BP125557) Brooks Landing - 12,981m2, Group E building, sprinklered, combustible construction, fire alarm, BCBC 2012 - 3.2.2.65, subdivided into 3 separate buildings with two firewalls by 1996 Equivalency. Equivalency required 1 hr fire separations between tenants of Group D and E occupancies and a 2 hrs fire separation between Group A2 and Group E occupancies. |
Application Status: | COMPLETED |
Permit Value: | $30,000.00 |
Issued Date: | January 08, 2020 |
File Close Date: | June 15, 2020 |
Expiry Date: | January 07, 2022 |
Associated Properties
Address | Zone | More |
---|---|---|
2000 ISLAND HIGHWAY N | CD8 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
CANCELLED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
FAILED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2020-06-15 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.