BP125834 - 1600 Dufferin Crescent (209, 309, 311, 411)
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP125834 - 1600 Dufferin Crescent (209, 309, 311, 411) | |
---|---|
Neighbourhood: | Northfield |
Street Address: | 1600 Dufferin Crescent (209, 309, 311, 411) |
Type of Application: | Commercial / Multi-Res Alteration |
File Number: | BP125834 |
Date Application Submitted: | September 12, 2019 |
Application Description: |
Units # 209,309, 311 & 411 - Demolition of 4 exterior balconies with deterioration of framing members, replace with Structural Engineer's design. The size of balconies 411 & 311 will be reduced to 8.12m2. |
Application Status: | COMPLETED |
Permit Value: | $25,000.00 |
Builder: | TIDALWEST BUILDING PROJECTS LTD |
Issued Date: | November 18, 2019 |
File Close Date: | August 27, 2024 |
Expiry Date: | November 17, 2021 |
Associated Properties
Address | Zone | More |
---|---|---|
1600 DUFFERIN CRESCENT | R1 | Property Report |
209 1600 DUFFERIN CRESCENT | R1 | Property Report |
309 1600 DUFFERIN CRESCENT | R1 | Property Report |
311 1600 DUFFERIN CRESCENT | R1 | Property Report |
411 1600 DUFFERIN CRESCENT | R1 | Property Report |
Process Steps
Task | Status |
---|---|
EXCAVATION
Excavation of soil, prior to placing forms |
PASSED |
FOOTING/FORMS
Inspection of forms prior to any concrete being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
MONITORING FIELD REVIEW
A building official may attend the site from time to time during the course of construction to ascertain that the field reviews are taking place and to monitor the field reviews undertaken by the registered professional. |
FAILED |
FINAL
Final approval as per requirements on plans. |
PASSED
2024-08-27 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.