Neighbourhood: | Downtown/Old City |
Street Address: | 1 Chapel Street |
Type of Application: | Commercial / Multi-Res Alteration |
File Number: | BP125785 |
Date Application Submitted: | August 26, 2019 |
Application Description: |
(Seacrest Apartments) -17 Storey, Constructed under 1960 NBC, Group C Division 1, Any Height, Any Area, unsprinklered, non-combustible construction. Permit required to resolve CIB03754, (Scope of work) - NE corner of bldg to include the removal of 3 pcs. bathroom, kitchenette and suite entry doors for floors 3-16. Removal and capping of illegal washroom on each floor 3-16. Apartments ( TYPE X01) to be returned to 2 bedroom apartments with 1 HR Fire separation between each unit. Structural Eng. is involved for design and review of repair of the concrete suspended floor opening in observation lounge. (Existing illegal suites) NW corner of bldg floors 11, 12 - Create 1 bedroom suites (TYPE X05A), inspections of installation of 3 pcs. bathrooms and kitchen sinks. Removal of all construction regarding the illegal penthouse suite including plumbing, re install required exit stairway with all required life safety items and return to previously approve use observation lounge area. Rev 2021 |
Application Status: | COMPLETED |
Permit Value: | $350,000.00 |
Issued Date: | November 28, 2019 |
File Close Date: | January 17, 2023 |
Expiry Date: | November 29, 2021 |
Associated Properties
Address | Zone | More |
---|---|---|
1 CHAPEL STREET | DT5 | Property Report |
Process Steps
Task | Status |
---|---|
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
FAILED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
PLUMBING FINAL
All fixtures must be in place. |
PASSED |
APPROVAL-FIRE
Approval required prior to Occupancy |
APPROVED |
FINAL
Final approval as per requirements on plans. |
FAILED |
FINAL
Final approval as per requirements on plans. |
CANCELLED |
FINAL
Final approval as per requirements on plans. |
CANCELLED |
FINAL
Final approval as per requirements on plans. |
FAILED |
FINAL
Final approval as per requirements on plans. |
PASSED
2023-01-17 |
Map |
---|
|
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.