BP125785 - 1 Chapel Street

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP125785 - 1 Chapel Street
Neighbourhood: Downtown/Old City    
Street Address: 1 Chapel Street
Type of Application: Commercial / Multi-Res Alteration
File Number: BP125785
Date Application Submitted: August 26, 2019
Application Description: (Seacrest Apartments) -17 Storey, Constructed under 1960 NBC, Group C Division 1, Any Height, Any Area, unsprinklered, non-combustible construction.
Permit required to resolve CIB03754, (Scope of work) - NE corner of bldg to include the removal of 3 pcs. bathroom, kitchenette and suite entry doors for floors 3-16. Removal and capping of illegal washroom on each floor 3-16. Apartments ( TYPE X01) to be returned to 2 bedroom apartments with 1 HR Fire separation between each unit. Structural Eng. is involved for design and review of repair of the concrete suspended floor opening in observation lounge. (Existing illegal suites) NW corner of bldg floors 11, 12 - Create 1 bedroom suites (TYPE X05A), inspections of installation of 3 pcs. bathrooms and kitchen sinks.
Removal of all construction regarding the illegal penthouse suite including plumbing, re install required exit stairway with all required life safety items and return to previously approve use observation lounge area.
Rev 2021
Application Status: COMPLETED
Permit Value: $350,000.00
Issued Date: November 28, 2019
File Close Date: January 17, 2023
Expiry Date: November 29, 2021

Associated Properties

Address Zone More
1 CHAPEL STREET DT5 Property Report

Process Steps

Task Status
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PASSED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PASSED
PLUMBING FINAL

All fixtures must be in place.

PASSED
APPROVAL-FIRE

Approval required prior to Occupancy

APPROVED
FINAL

Final approval as per requirements on plans.

FAILED
FINAL

Final approval as per requirements on plans.

CANCELLED
FINAL

Final approval as per requirements on plans.

CANCELLED
FINAL

Final approval as per requirements on plans.

FAILED
FINAL

Final approval as per requirements on plans.

PASSED

2023-01-17

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy