BP125485 - 100 & 200 - 1955 Boxwood Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP125485 - 100 & 200 - 1955 Boxwood Road | |
---|---|
Neighbourhood: | Northfield |
Street Address: | 100 & 200 - 1955 Boxwood Road |
Type of Application: | Commercial / Multi / Industrial |
File Number: | BP125485 |
Date Application Submitted: | May 06, 2019 |
Application Description: |
(VI Granite & Quartz Countertops) Construction of a new 2 storey 699.4 m2 Industrial (F2) building with subsidiary showroom(E) and 2nd floor residential(C). BCBC 2018 Building Classifications:3.2.2.79(F2); 3.2.2.53(C) 2 storey, Combustible/Non Combustible Construction, Building is sprinklered with fire alarm system. Loadbearing walls, columns and arches supporting structural elements require a FRR not less than the supported assembly (1hr) Building includes; Unit 100- 529.09 m2 of warehouse (F2); 170.3m2 of subsidiary Showroom (E); and Unit 200- 117.61 m2 of Residence (C) on the 2nd floor. 2hr FRR/FS required between 2nd Floor Residence (C) and Warehouse (F2). 1 hr FRR/FS- Between Residence (C) to Showroom (E). 2 Hr fire separation provided between Showroom (E) and Warehouse (F2). 2 Hr Non combustible wall required on south side. REVISION:May.12,2020- Added upright sprinklers void areas. |
Application Status: | COMPLETED |
Permit Value: | $1,243,439.00 |
Builder: | ISLAND WEST COAST DEVELOPMENTS LTD |
Issued Date: | November 05, 2019 |
File Close Date: | July 20, 2020 |
Expiry Date: | November 04, 2021 |
Associated Properties
Address | Zone | More |
---|---|---|
1955 BOXWOOD ROAD | I2 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
CANCELLED |
FOOTING/FORMS
Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
FIRELINE
Fireline for the sprinkler system must be complete and visable for inspection. |
PASSED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
FAILED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
CANCELLED |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PARTIAL |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PARTIAL |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PASSED |
STORM CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
SANITARY CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PARTIAL |
WATER CONNECTION
Pipe and connection must be visible for inspection. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PARTIAL |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
FAILED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
FAILED |
SPRINKLER FINAL
Sprinkler system must be complete and operating as intended. |
PASSED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
SCHEDULED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
FAILED |
PLUMBING FINAL
All fixtures must be in place. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
SCHEDULED |
APPROVAL-FIRE-OLD
Approval required prior to Occupancy |
COMPLETED |
OCCUPANCY-OLD | FAILED |
OCCUPANCY |
PASSED
2020-07-20 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.