BP125281 - 232 Manning Street
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP125281 - 232 Manning Street | |
---|---|
Neighbourhood: | University District |
Street Address: | 232 Manning Street |
Type of Application: | Garage / Carport Permit |
File Number: | BP125281 |
Date Application Submitted: | March 01, 2019 |
Application Description: |
For the construction of a 436 sq.ft. detached garage 2019-AUG-22 REVISION: add geotech. tjw |
Application Status: | COMPLETED |
Permit Value: | $28,711.74 |
Building Area: |
40.48 M2 435.72 ft2 |
Builder: | SUN PORCH HOMES LTD |
Issued Date: | March 29, 2019 |
File Close Date: | October 03, 2019 |
Expiry Date: | March 29, 2021 |
Associated Properties
Address | Zone | More |
---|---|---|
232 MANNING STREET | R1B | Property Report |
236 MANNING STREET | R14 | Property Report |
Process Steps
Task | Status |
---|---|
FOOTING/FORMS
Inspection of forms prior to any cement being poured . For footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite. |
PARTIAL |
FOOTING/FORMS
Inspection of forms prior to any cement being poured . For footing inspection, forms must be complete and approved plans (complete with City Stamp) must be onsite. |
PASSED |
PERIMETER DRAIN
For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering. |
PASSED |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PASSED |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PARTIAL |
PAPER/FLASHING/WATERPROOFING
When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco. |
PASSED |
FRAMING
Rough-in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
FAILED |
FRAMING
Rough-in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
FINAL-OLD
Final Approval as per requested on plans. |
PASSED
2019-10-03 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.