Application Description: |
Tenant Improvement- (Tim Hortons) Bldg A, 2018 BCBC, 3.2.2.27, Group A2 Occupancy, 243.68 m2, single storey, combustible construction, sprinklered with fire alarm system. One accessible washroom, one unisex washroom and one staff washroom. REVISION: Oct.16/19 - Change location of water line. REVISION 2: Nov. 5/19 - Reverse accessible washroom and unisex washroom locations. |
Application Status: | COMPLETED |
Permit Value: | $550,000.00 |
Issued Date: | July 18, 2019 |
File Close Date: | December 27, 2019 |
Expiry Date: | July 19, 2021 |
Associated Properties
Address | Zone | More |
---|---|---|
601 BRUCE AVENUE | CC3 | Property Report |
Process Steps
Task | Status |
---|---|
FIRELINE
Fireline for the sprinkler system must be complete and visible for inspection. |
PARTIAL |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
Complete underslab plumbing must be visible. |
PASSED |
UNDERSLAB INSULATION
Inspection required prior to placing slab concrete. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visible for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visible for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visible for inspection. |
PASSED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
FAILED |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing and electrical must be complete. Survey Certificate and Truss Layouts required for approval. |
PASSED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
FAILED |
INSULATION
Insulation and vapour barrier to be complete prior to inspection. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
APPROVAL-FIRE-OLD
Approval required prior to Occupancy |
COMPLETED |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD | FAILED |
OCCUPANCY-OLD |
PASSED
2019-12-27 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.