BP125141 - 1875 Boxwood Road (BLDG B)

Interested in this application? Login to manage subscriptions to subscribe to updates!

Search Again
BP125141 - 1875 Boxwood Road (BLDG B)
Neighbourhood: Northfield    
Street Address: 1875 Boxwood Road (BLDG B)
Type of Application: Commercial / Multi / Industrial
File Number: BP125141
Date Application Submitted: December 06, 2018
Application Description: Dummy Permit
Building B: 1,835.72 m2 Building Area Classified under 3.2.2.75. Group F2 up to 4 storeys, sprinklered. Combustible or non-combustible construction permitted. Floors, mezzanines and loadbearing assemblies require 45 min FRR/FS. North facing exterior wall requires a 2 hr FRR.

REVISION: May 7, 2020 - BLDG B - Create 8 units with 45 min F.R.R. F.S. Add 2nd storey, accessible washrooms and roughed in second 3 piece washroom and sink in each unit, washrooms also added to 4 second floor units. Revise Structural.
REVISION: JAN.7/21 - BLDG B - Add 2 piece washroom to upper floor of units 105 - 108.
Application Status: COMPLETED
Issued Date: June 12, 2019
File Close Date: July 22, 2021
Expiry Date: June 11, 2021

Associated Properties

Address Zone More
1875 BOXWOOD ROAD Property Report

Process Steps

Task Status
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PARTIAL
FOOTING/FORMS

Inspection of forms prior to any cement being poured. For footing inspection, forms must be complete and approved plans (complete with City stamp) must be onsite.

PASSED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

FAILED
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PARTIAL
PERIMETER DRAIN

For perimeter drain, foundation walls should be damp proofed and drain tile in place with drain rock covering.

PASSED
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PARTIAL
UNDERSLAB PLUMBING

complete underslab plumbing must be visible.

PASSED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PARTIAL
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PARTIAL
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PARTIAL
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

FAILED
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PARTIAL
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PARTIAL
UNDERSLAB INSULATION

Inspection required prior to placing slab concrete.

PASSED
STORM CONNECTION

Pipe and connection must be visible for inspection.

PASSED
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
SANITARY CONNECTION

Pipe and connection must be visible for inspection.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

CANCELLED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

FAILED
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PARTIAL
ROUGH IN PLUMBING

Rough in plumbing must be complete including potable water piping.

PASSED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

FAILED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PARTIAL
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

FAILED
PAPER/FLASHING/WATERPROOFING

When framing, sheathing, building paper, flashing, weatherproofing of openings and window installation is complete, but before installation of any siding, wire mesh or stucco.

PASSED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

CANCELLED
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PARTIAL
ROUGH IN SPRINKLER

Rough in sprinkler must be complete and visable for inspection.

PASSED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

FAILED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

CANCELLED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

CANCELLED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

CANCELLED
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
FRAMING

Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

CANCELLED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

FAILED
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
INSULATION

Insulation and vapour barrier to be complete prior to inspection.

PARTIAL
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

FAILED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

FAILED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

FAILED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

FAILED
SPRINKLER FINAL

Sprinkler system must be complete and operating as intended.

PASSED
PLUMBING FINAL

All fixtures must be in place.

FAILED
PLUMBING FINAL

All fixtures must be in place.

FAILED
PLUMBING FINAL

All fixtures must be in place.

FAILED
PLUMBING FINAL

All fixtures must be in place.

FAILED
PLUMBING FINAL

All fixtures must be in place.

PASSED
OCCUPANCY FAILED
OCCUPANCY FAILED
OCCUPANCY FAILED
OCCUPANCY CANCELLED
FINAL

Final approval as per requirements on plans.

FAILED
FINAL

Final approval as per requirements on plans.

PASSED

2021-07-22

Map
View in Google Earth (KML)


Disclaimer:

The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo. Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation. The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.

The Information Provided within this website is for Informational Purposes Only. It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.

Help us improve our website

Don't include private or financial information in this form.

Collection and use of your personal information
Information collected on this form is done so under the general authority of the Community Charter and Freedom of Information and Protection of Privacy Act (FOIPPA), and is protected in accordance with FOIPPA.  Personal information will only be used by authorized staff to fulfill the purpose for which it was originally collected, or for a use consistent with that purpose. Questions about the collection of your personal information may be referred to the Legislative Services Department at (250) 755-4405, or via email at foi@nanaimo.ca.
Privacy Policy