BP125040 - 101 - 4735 Rutherford Road
Interested in this application? Login to manage subscriptions to subscribe to updates!
Search AgainBP125040 - 101 - 4735 Rutherford Road | |
---|---|
Neighbourhood: | Rutherford |
Street Address: | 101 - 4735 Rutherford Road |
Type of Application: | Commercial / Multi-Res Alteration |
File Number: | BP125040 |
Date Application Submitted: | December 04, 2018 |
Application Description: | (Fit 4 Less) - Building classified as 3.2.2.24, Group A-2 occupancy, 1386 m2 sprinklered, fire alarm system. 2hr FRR between suites (BP121831), 1hr FRR between unit and rear corridor (existing). Total occupant load of 150 persons. Addition of 3 new shower rooms and installation of accessible shower facility in existing H/C washroom #115, install 3 new pendant sprinkler heads. |
Application Status: | COMPLETED |
Permit Value: | $50,000.00 |
Issued Date: | January 15, 2019 |
File Close Date: | June 28, 2019 |
Expiry Date: | January 15, 2021 |
Process Steps
Task | Status |
---|---|
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PARTIAL |
UNDERSLAB PLUMBING
complete underslab plumbing must be visible. |
PASSED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PARTIAL |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
CANCELLED |
ROUGH IN PLUMBING
Rough in plumbing must be complete including potable water piping. |
PASSED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PARTIAL |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
CANCELLED |
ROUGH IN SPRINKLER
Rough in sprinkler must be complete and visable for inspection. |
PASSED |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PARTIAL |
FRAMING
Rough in plumbing & electrical must be complete. Survey Certificate & Truss layouts required for approval. |
PASSED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PARTIAL |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
CANCELLED |
SPRINKLER FINAL-OLD
Sprinkler system must be complete and operating as intended. |
PASSED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PARTIAL |
PLUMBING FINAL-OLD
All fixtures must be in place. |
CANCELLED |
PLUMBING FINAL-OLD
All fixtures must be in place. |
PASSED |
FINAL-OLD
Final approval as per requirements on plans. |
CANCELLED |
FINAL-OLD
Final approval as per requirements on plans. |
FAILED |
FINAL-OLD
Final approval as per requirements on plans. |
PASSED
2019-06-28 |
Map |
---|
![]() |
Disclaimer:
The City of Nanaimo does not endorse any information contained herein by parties not affiliated with the City of Nanaimo.
Furthermore, the City of Nanaimo is providing the information contained within this website without warranty, guarantee, or further obligation.
The City is not liable for any consequences or damages any individual may incur as a result of misrepresented, misquoted, or mistaken information.
The Information Provided within this website is for Informational Purposes Only.
It is not meant to be an authoritative guide, and will not in any circumstances override any decisions or standards made or set by any representative or agent of the City of Nanaimo.